How SCRUM Made Our Office Move Great

by Joanna Pineda Posted on August 5, 2009

Office moves are never fun. Our move was months in the planning, but we were still scrambling last Friday night, the day before the movers arrived.  The plan was to complete the physical move on Saturday, then have all staff come in on Sunday to set-up their own work areas, test the network and phones, and help unpack the common areas. There were a million tasks to be done? How was it all going to get done? Then we had a great idea: let’s use SCRUM, do a one-day sprint and complete as much of the move as possible. Here’s what we did, with amazing results.

Office Move To Do List

Here is our Office Move To Do List at the start of the day on Saturday.

Everyone who came in on Sunday helped.  Some people completed a lot of tasks, while others completed just one.  What mattered was that so many tasks that normally get delegated to the admins got done.  The Director of Client Services wiped all the white boards clean then distributed them.  A senior Developer wiped down the credenzas in the conference room.  A Project Manager put up the bulletin board in the kitchen.  Three staff members unpacked the kitchen.

To Do List + Done List

Here is To Do List next to our Done List by Sunday evening.
Nearly all remaining tasks were done by Wednesday afternoon.

The results were unbelievable. By Sunday evening:

The best part?  Instead of the move being a drag, we had a party! (Doughnuts, pizza, music and beer helped!)  And I didn’t hear complaints about how things weren’t working as planned because everyone helped and knew how hard the admins and net admins had been working to ensure a smooth move!

We’re now trying to figure out how to use a similar process for other, non-technical projects at Matrix Group.  How about you?  How have you used SCRUM in unique ways and situations to get a project done and done well?